Creating MS Project based on Start +X days
MS Project does need calendar dates in order to create a schedule. However, you can format the Gantt chart to show the timescale as a reference to the start of the project.
To do this, double-click the timescale to bring up the format options and change the label on the top/middle/bottom tiers as desired.