Giving up Agile, Switching to waterfall - Is this right? [closed]
First off - ask yourself are you really doing Agile? If you are then you should have already delivered a large portion of usable functionality to the client which satisfied their requirements in the earlier sprints. In theory, the "damage" should be limited to the final sprint where you discovered you needed large design changes. That being the case you should have proven your ability to deliver and now need a dialogue with the client to plan the changes now required.
However given your description I suspect you have fallen into the trap of just developing on a two week cycle without actually delivering into production each time and have a fixed end date in mind for the first proper release. If this is the case then you're really doing iterative waterfall without the requirements analysis/design up front - a bad place to be usually.
Full waterfall is not necessarily the answer (there's enough evidence to show what the problems are with it), but some amount of upfront planning and design is generally far preferable in practice to the "pure" Agile ethos of emergent architecture (which fits with a Lean approach actually). Big projects simply cannot hope to achieve a sensible stable architectural foundation if they just start hacking at code and hope it'll all come good some number of sprints down the line.
In addition to the above another common problem with "pure" Agile is client expectation management. Agile is sold as this wonderful thing that means the client can defer decisions, change their mind and add new requirements as they see fit. HOWEVER that doesn't mean the end date / budget / effort required remains fixed, but people always seem to miss that part.
The agile development methodologies are particularly appropriate when you have unclear requirements and when you may need to make design changes at later stages in your project. Waterfall is a less appropriate approach in this case. The waterfall approach is appropriate for projects which are well understood and when the requirements are unlikely to change during the project's lifetime. It doesn't sound like that is the case here.
How long are your sprints? An alternative approach might be to decrease the sprint length - at least at the start of the project. Deliver new versions to the customer more often and discuss the changes with the customer. If you aren't doing what they want this will become apparent more quickly so less time will be wasted on implementing solutions that don't meet the customer's requirements.
I'm not sure what kind of shop you run, so it's hard for me to come up with good recommendations. I can offer two guiding principles though:
- If you have bad communication with the customer, no development methodology will save you.
- It's none of the diner's business how a chef organizes the kitchen, as long as the meal is tasty.
It sounds like you have serious project management and architecture/design issues, and it sounds like your communications have also broken down. Fundamentally I don't think changing your dev methodology is going to fix any of that, and is therefore the wrong thing to be doing (though it may restore some client confidence).
I would be especially concerned about moving towards waterfall since you are now choosing to essentially capture the requirements just once (which we know you have a problem with) with no capacity for input. That rigidity is good for inflexible delivery targets, but it's completely inappropriate here where you have changes all the time - that's agile!
Short term I'd step back and double check your requirements at this stage with them. Renegotiate and confirm your current state in relation to those.
Medium term, I'd open up more communications with the client - try and get them involved in a daily scrum for a while (until you restore confidence, then you can be more flexible).
Long term, you have to be worried about how your PM's and senior devs have managed to get you into this position. If the client is being unreasoanable that's one thing (but it's still up to the PM to manage that, so you're not absolved). It's not reasonable to complain about having too many changes, that just means you screwed up in determining requirements (which is a dialogue, not a monologue) or that you have to have more numerous, but probably shorter sprints.
Above all, I can't see moving towards waterfall is possibly correct. It doesn't fix anything directly and I can only see it exacerbating the problems you've already highlighted.
Caveat: I'm not really capable of a balanced view on waterfall since I've never seen it work effectively and imho it's just completely outdated for enterprise projects.